Hilton Hotel Site Remediation, Government of Barbados

project details

Client: Government of Barbados
Project Details: Needhams Point Holdings Limited Barbados Hilton Site Remediation
Client Location: Needham's Point St Michael Bridgetown, 11000 Barbados

Let’s Start Work
Together

Please feel free to contact us. We will get back to you with 1-2 business days. Or just call us now.

Project Background

Hilton Hotels were seeking to demolish and rebuild a new hotel in their existing site at Needham’s Point. The site was found to be contaminated with petroleum contaminants from both the adjacent former refinery site as well as fuel leakage from holding tanks on the Hilton site.

Objective

To reduce Total Petroleum Hydrocarbon (TPH) to less than 5000 parts per million (ppm), from concentrations of 700,000 ppm and greater.

Result

The Fiton Biocatalysis process achieved the remediation objective. The Ministry of Physical Development and Environment (Energy Division) wrote the following after completion of the project, “the Fiton biocatalysis process achieved a level of cleanup that the Ministry did not believe possible and as a result, the Ministry unconditionally endorses the process for future use in cleaning up other areas of contamination on the Island of Barbados.”